This chapter is a route. If you have just installed the equipment, follow it and by the end of the first week you will have an Aquarino KH tuned to your aquarium — and, more importantly, the confidence of knowing why it is tuned that way.
Day 1 — install and calibrate
- Install the equipment, the hose and the probe (Chapters 4 and 5).
- Install the app, create your account and add the equipment (Chapters 6 and 7).
- Run a full calibration with a chemical test you trust (Chapter 10).
- Set target and margin (Chapter 14). Leave correction off for now.
- Set the interval to 1 hour and notification to Always.
Days 2 and 3 — observe
- Change nothing. Let the equipment measure.
- Once a day, open Graphs and look at the last 24 hours.
- Check the aeration in both chambers (Chapter 13) — it is the adjustment that most affects reading quality.
By the end of the third day you should be able to answer: what is my aquarium's daily KH swing, and does it follow the photoperiod?
Day 4 — check against the chemical test
- Run a chemical test at the same time of day and from the same collection point as the equipment.
- Compare it with the value measured at that hour.
- If the difference is smaller than your kit's margin of error (± 0.30 dKH), all is well — do not recalibrate.
- If it is larger, run a partial calibration (Chapter 11).
Days 5 and 6 — turn correction on
- If you use 3-in-1 balling or want the safety net: set the Buffer Doser to Normal and calibrate the pump (Chapter 16).
- If you use a calcium reactor: enable the Co2 Port and start watching the hourly percentages (Chapter 17).
- Follow the event log in Logs to see the decisions the equipment is making.
Day 7 — adjust and settle
- Calcium reactor: set the bubble counter so the port lands in the ideal ranges (75–90% during the photoperiod, 15–30% outside it).
- Doser: if you see daily-limit warnings, the problem is your main replenishment, not the Aquarino KH.
- Change notification from Always to Off target.
- If the system is steady, you can raise the measurement interval to 2–4 hours — unless you are using the Co2 Port, which requires the hourly cadence.